| Application |
| This general purpose liquid or gas switch package provides a low flow detection solution for pump or process protection with a 1A relay interface for remote devices such as a PLC, SCADA or alarm. The short sensor is intended for use in pipe or ducting from 1/2" to 11/2"; the long sensor is applied in 2" and up. The product is broadly selected for low or no-flow applications. Specify the appropriate sensor technology, length and material. |
|
| Features |
|
| |
| |
1A relay selectable NO or NC via power supply wiring polarity |
| |
PP enclosure rated NEMA 4X with 300° conduit swivel base |
| |
PP or PVDF wetted material for challenging corrosive fluids |
| |
Compatible with Flowline controller, alarm and fitting accessories |
|
| Tech Tip |
The NEMA 4X enclosure is made of UL approved fire retardant PP and features a 300° swivel base for easy conduit alignment. The power and switch terminals are prewired to the terminal strip,.  |
 |
|
|
|
|
Specifications
|
|
Set point range:
|
FT10: 0.04 to 3 fps (0.012 to 0.91 mps) GT10: 1 to 90 fps (0.3 to 27 mps)
|
|
Repeatability:
|
±0.5% of set point
|
|
Supply voltage:
|
12-36 VDC
|
|
Contact type:
|
(1) SPDT relay
|
|
Contact rating:
|
60 VA
|
|
Process temp:
|
F: 32° to 140° C: 0° to 60°
|
|
Pressure:
|
150 psi (10 bar)
|
|
Wetted material:
|
PP-Ryton®/PVDF
|
|
Conduit entrance:
|
1/2" NPT
|
|
Enclosure rating:
|
NEMA 4X (IP65)
|
|
Process mount:
|
3/4" NPT (3/4" G)
|
|
Classification:
|
General purpose
|
|
 |
|