back to list

FloaTek Two-Wire Float Level Transmitter

Introducing FloaTek™ Two-Wire Float Level Transmitter

Application
Offered in FM and CSA approved explosion proof or general purpose configurations, the two-wire float transmitter provides contact level measurement up to 6' or 1.8m, and is ideally suited for relatively clean water, light oil or diluted corrosive liquids. The transmitter is typically selected for high temperature and/or pressure process tank applications located within a classified hazardous or general purpose area. Media examples include hot water and cooking oil.


Flowline FloaTek
Features
  Explosion proof transmitter for use in hazardous environments
  Rugged 316 stainless steel float, guide and 2" NPT mounting plug
  Compatible with Flowline remote indicator and relay controllers
  Custom assembled to your guide length and span dimensions
Tech Tip
Perfect for high temperature and pressure applications, the LV51-S001 explosion proof transmitter is provided with a rugged cast aluminum enclosure rated NEMA 7. Its hazardous level made simple.
   
Specifications
Range:
5" to 6' (12.7cm to 1.8m)
Accuracy:
± 0.25% over span in water
Specific gravity:
0.75 minimum
Supply voltage:
LV50: 10 to 30 VDC
LV51: 10 to 40 VDC
Signal output:
4-20 mA, two-wire
Calibration:
None, fixed span
Process temp.:
F: -5° to 125°
C: -20° to 50°
Pressure:
300 psi (20 bar)
Conduit:
1/2" NPT
Enclosure rating:
NEMA 4X (IP65) / NEMA 7
Process mount:
2" NPT
Guide/float mat:
316 ss
Classification:
LV50: General purpose
LV51: Explosion proof
Part Numbers

Comments
(Please login/register to leave a comment)
Back to Top